LWP were appointed as Quantity Surveyor on this factory extension. The extension was constructed within the service yard which attached onto the delivery/area and so, the extension had to be built around the ongoing deliveries with the final works undertaken over the 2-week factory closedown.

The contract period was 28 weeks with a contract sum of £500,000.