Mecaplast, Peterlee

LWP were appointed as Employers Agent and Principal Designers on this project which involved the extension to an existing manufacturing facility, whilst the existing facility continued to operate. At the date of our appointment, a main contractor had been appointed although the specification and cost hadn’t been fully concluded. We successfully negotiated this project and, working hand in hand with the contractor and his design team, together with the client, we delivered a successful project.

The contract period was 29 weeks with a contract sum of £2M

.